PROJECTS PORTFOLIO   |   Civil Engineering

Maudlin Waste Water Treatment Plant

Project Details

Contract:Maudlin Industrial Estate Water Treatment Plant, Naas, Co. Kildare
Client:QK Coldstores Ltd
Year:2009
Contract Details:

This contract involved the construction of an over ground waste water treatment tank with a capacity of 3,600,000 litres. Roadform Ltd were PSCS for the works which involved the supply of plant, labour & materials. Construction involved the supply & fixing of 140 tonne of reinforcing steel, the supply & placing of 1,500m3 of concrete, 300 linear metres of contraction joints, water bar, tanking and 2,200m2 of formwork. The works were completed to a high quality finish on programme within a confined site.